Wren Kitchens Bolton

Shell works of retail unit in Bolton

The works at Wren Bolton were carried out over a 12 week period and included:

  • Strip out of existing retail unit including removal of floor finishes and diamond grinding or shot blasting of sales floor area.
  • Removal of existing front elevation low level glazing, breaking out masonry panels and taking off existing cladding.
  • Steelwork alterations to provide for the installation of new full height curtain walling glazed windows.
  • Floor slab and stall riser works in readiness for new shop fronts.
  • Installation of new fully glazed shop fronts including new auto entrance doors.
  • New cladding and brickwork to complete the front elevation.
  • Pressure cleaning of existing signage towers and bullnose details. Specialist spraying of retained steelwork and cladding.
  • Roofing and gutter works to include new gutter lining, cut edge protection to roof sheets, removal of ducts, installation of roof lights.
  • Re-laid and renewed paving to front of showroom, installed new bollards and kurbs.

Take a look at Wren Bolton's website - www.wrenkitchens.com/showrooms/bolton

Talk to us

If you have any questions about our products or services then please do not hesitate to contact us.

Tel: 0800 0282307

Other Case Studies